Every year Keller Williams Realty has what they call a Red Day. On this day they select a service project to help out the community with and all of the employees participate. For the past two years, Keller Williams has helped the Patrick Henry Downtown Academy. It was certainly the most exciting day on the site! THANK YOU to all of the volunteers who came out to help us.
The Washington University Design Build Studio is a design team at Washington University working with Patrick Henry Downtown Academy to transform the elementary school’s grounds into a landscape that encourages healthy play and outdoor learning.
Friday, May 13, 2011
Keller Williams Realty Red Day
Every year Keller Williams Realty has what they call a Red Day. On this day they select a service project to help out the community with and all of the employees participate. For the past two years, Keller Williams has helped the Patrick Henry Downtown Academy. It was certainly the most exciting day on the site! THANK YOU to all of the volunteers who came out to help us.
Thursday, May 12, 2011
On Site Final Review
Saturday, May 7, 2011
Pope Family Shout Out
Trees!
Tuesday, May 3, 2011
Dry Creek Bed
With all of the rain these past 2 weeks it’s pretty clear that our dry creek bed will be needed. We began by digging a trench around the mounds. We then added geotextile filter fabric and gravel. This will help drain the water to two big holes on the site. At these two spots we added drainage pipe that can be used to check and see how well the site is draining.
Friday, April 29, 2011
Mound Making
Tuesday, April 26, 2011
‘Bamboos’ Barrier
Thursday, April 21, 2011
Planting Plan
Our Sign!
Wednesday, April 20, 2011
Removing the Asphalt
With the work on the south side of the project getting closer to completion we needed to start removing the asphalt from the rest of the schoolyard. At the beginning it seemed intimidating, but we dug deep and found the confidence to remove it. Even Principal Veal got into the Bobcat to help us out.